BOQ vs BOM: what's the difference and why it matters

EngiERP team · 6 min read

If you build machines, structures or panels to order, you have probably used both terms, sometimes interchangeably. They are not the same thing, and mixing them up is one of the most common reasons project costs drift without anyone noticing.

What is a BOM?

A bill of materials (BOM) describes how to build one item. It lists the components, sub-assemblies and quantities needed to make a single unit, often over several levels. A gearbox BOM lists its housing, shafts, gears and bearings. The housing may have its own BOM.

  • Scope: one item, reused across many orders
  • Owner: engineering or design
  • Used for: production orders, material issue, MRP and costing

What is a BOQ?

A bill of quantities (BOQ) lists everything one project needs. It includes items you make, items you buy, work you outsource, and services done at site such as installation or commissioning. It is usually grouped into sections such as Frame, Electricals or Site Work, and carries estimated rates.

  • Scope: one customer order or project
  • Owner: projects, estimation or sales engineering
  • Used for: budgeting, procurement, progress and variance

BOQ vs BOM at a glance

BOMBOQ
DescribesHow one item is builtWhat one project needs
ContainsComponents and sub-assembliesMade, bought and outsourced items, plus services
QuantitiesPer unit of the parent itemTotals for the whole project
RatesUsually from standard costEstimated rates for the project
Changes throughEngineering change and revisionBOQ revision with approval

Why the link between them matters

In many companies the BOQ lives in Excel and the BOM lives in the ERP or in a CAD export. Purchase works from one, production from the other, and nobody compares them with what was actually issued from stores. The result is familiar:

  • The same requirement is bought twice, once as a component and once as a BOQ line.
  • Excess material is issued to the shop floor without anyone noticing.
  • The project's real material cost is known only after it closes.

How to connect BOQ and BOM properly

  1. Fill the BOQ from released BOMs so made assemblies explode into the right components.
  2. Avoid double counting. A requirement belongs either in the assembly's BOM or as a separate BOQ line, never both.
  3. Approve and freeze the BOQ against the approved drawing revision before buying starts.
  4. Create requisitions and production orders from the BOQ so they cannot exceed approved quantities.
  5. Compare issues with the BOQ continuously, and require a reason for anything beyond it.
  6. Revise, don't overwrite. Keep the original estimate next to the current approved one.

How EngiERP does it: Make-to-order projects in EngiERP include a BOQ that can be filled from BOMs or imported from Excel. Approval freezes it against the drawing revision. Purchase requisitions and production batches are created against it, and consumption is compared with it automatically. See the MTO workflow →